AT THE TIME OF BOOKING AND REGISTRATION | 25% of unit cost |
WITHIN 15TH DAYS FROM FINALISATION OF FLAT WITH TOKEN | 10% of unit cost |
ON COMPLETION OF 1ST FLOOR CASTING | 10% of unit cost |
AT THE TIME OF 2ND FLOOR ROOF SLAB CASTING | 10% of unit cost |
AT THE OF 3RD FLOOR FOOF SLAB CASTING | 10% of unit cost |
AT THE TIME OF 4TH FLOOR ROOF SLAB CASTING | 10% of unit cost |
AT THE TIME OF BRICK WORK 1ST FLOOR | 10% of unit cost |
BEFORE ON MONTH FROM THE DATE OF POSSESSION | 5% of unit cost |